Watermain Shutdown - Colgan Development 1& 2

Posted on Thursday, March 09, 2023 09:16 AM

MARCH 9, 2023PROJECT NO: 1000-3958-EW211000-4243-EW21

RE: TRIBUTE COLGAN 1 & 2 DEVELOPMENTSOUTHWEST CORNER OF CONCESSION RD 8 AND COUNTY ROAD 14 INTERSECTION; AND,NORTHWEST CORNER OF CONCESSION RD 8 AND COUNTY ROAD 14TOWNSHIP OF ADJALA-TOSORONTIO, COUNTY OF SIMCOE

To Whom It May Concern,

On behalf of the Owners, Tribute (Colgan) Ltd. & Tribute (Colgan 2) Ltd., we would like to inform all area residents and landowners that Pilen Construction, in coordination with the Township of Adjala-Tosorontio...

Road Closed

Road Closure Notice - Concession Rd. 8 - March 8th to 10th, 2023

Posted on Friday, March 03, 2023 12:58 PM

Road Closure - Concession Road 8

Please be advised that Concession Road 8 – Adj-Tos will be closed between County Road 14 and Magnolia Ave from Wednesday, March 8th to Friday, March 10th, 2023, from 9:00am to 3:30pm. This is a full closure for PVR installation and a Watermain connection.

The road will be closed north of property # 2139 Conc Rd 8 to North bound traffic.  The road will be closed south of property # 2139 Conc Rd 8 to South bound traffic.
  • All vehicles will be detoured through the new...

Road Closed

Road Closure Notice - Keenansville Rd - March 7th & 8th, 2023

Posted on Wednesday, March 01, 2023 04:13 PM

Road Closure Notice - Keenansville Road 

Please be advised that Keenansville Road will be closed at Concession Road 8 between Adj-Tec Townline and Concession Road 7 from Tuesday, March 7, 2023 – Wednesday March 8, 2023, from 9:00am to 3:30pm for Forced Main work.

The road will be fully closed to all through traffic at Conc. Rd 8 with all local traffic being detoured.

• All traffic in Keenansville must travel west to Concession Road 7.

We apologize for the inconvenience.

Township of Adjala-Tosorontio

Construction

Approved Works - Sunday January 8, 2023

Posted on Friday, January 06, 2023 02:08 PM

Tribute Communities - Colgan

Works have been approved for Sunday January 8th 2023 to install base and levelling plates at the Waste Water Treatment Plant. This work involves a 5 person crew that will be situated at the Northern part of the development where the plant is located. Hours are restricted from 8 a.m. to 4 p.m. Restrictions on heavy equipment have been placed for this day.

Any questions, please contact Chris Robinson - Chief Building Official at 705-434-5055 ext. 251 or by E-mail.

Image of Road Closures

Road Closure Notice: Construction on Paving County Rd 14 and Concession Rd 8

Posted on Monday, October 24, 2022 04:48 PM

Please note that Tribute (Colgan 1 & 2) will be scheduling paving operations on the following days:

  • Thursday, October 27, 2022 - County Road 14
  • Friday, October 28, 2022 - Concession Road 8 (south of County Road 14)
  • Saturday, October 29, 2022 - Concession Road 8 (north of County Road 14)

Contractor working hours are Monday to Friday 7:00 am to 7:00 pm and Saturday between 7:00 am and 3:00 pm.

Full details can be found with this link.

Notice

Structure 19 Updated Date of Completion

Posted on Thursday, October 13, 2022 03:04 PM

Township of Adjala-TosorontioNOTICE OF ROAD CLOSURE

Replacement of Structure 19 Concession Road 6, Township of Adjala-Tosorontio

***UPDATED EXPECTED COMPLETION DATE - NOVEMBER 28, 2022***

At present, the Structure Replacement is expected to be completed by October 31, 2022, however there is a possibility the construction may take longer based on uncertainties in the weather. Please ensure that your garbage is located at the end of your driveway by 7:00 a.m. on Thursday mornings for garbage pick-up...

Road Sign of Construction ahead

Colgan Development Site: Work has been approved for Saturday September 24, 2022

Posted on Thursday, September 22, 2022 08:36 AM

On behalf of the contractor working on the Colgan projects, please note that they will be working on Saturday September 24, 2022, from 7:00am to 3:00pm. 

The contractor will be working on the following tasks;

  • Work on Concession 8 and County Road 14 – deep sewer work and road crossings – this will avoid traffic interruptions which have been observed during the week
  • WWTP – advancement of rebar placement to advance concrete pours – this will get the plant out of the ground sooner so that weather is...